Asphalt Seal Coating Project: Day Two


Tomorrow will kick off day two of a seven-day seal coating project.  The below streets will be closed for a 24-hour period so that the seal coat can be applied and have time to dry. All travel and parking on these streets will be prohibited during this time.  

DAY 2 - Wednesday, June 22

  • HARIOT ALLEY
  • CORONADO TERRACE - 1/2 See Map
  • EDSON TERRACE
  • MAGELLAN SQUARE - 1/2 See Map
  • LUPINE ALLEY - Includes Legacy Park Drive #42612 - 42640, Golden Rod Drive #22926 - 22942
  • BLUEWING ALLEY
  • COURTLAND PARK HORSESHOE
  • DRAGONFLY ALLEY
  • PIPKIN ALLEY
  • ANGELIQUE DRIVE - # 22831 - 22855
  • ARBOR VIEW DRIVE - # 22830 - 22862
  • BROOKSHADE DRIVE - # 22766 - 22786
  • SWEET ANDREA DRIVE - # 22771 - 22787
  • ALLEY BEHIND #42600-42604 Legacy Park

RELOCATING VEHICLES: Vehicles remaining on these streets after 7:00 AM will be relocated to the Brambleton Town Center or a nearby VDOT street by a tow company.  Vehicles in residents’ driveways and garages will also need to be relocated by the owners if they plan or need to use their vehicle during the 24-hour road closure period.

ACCESS TO STREETS:  All access to the streets during this time is restricted.  Freshly applied seal coating will track.  Be sure to stay off the streets.  If applicable, educate and inform your children; also keep your pets off.  BCA will place plywood down in strategic locations to serve as crossing points for pedestrians.  

IRRIGATION SYSTEMS: If applicable, residents must turn off their irrigation systems during this 24-hour period.  Wet streets or water sprayed onto freshly seal coated street will negatively impact the application.  BCA will also be turning its systems off in the area of the treated streets.  

FURTHER INFORMATION: It is important that all affected residents understand how they will be impacted.  Please review the full information packet that was distributed to all impacted addresses.  This information is also on the BCA website at www.BrambletonHOA.com/asphalt.   If you have questions after reading this information, please email BCA's Capital Projects Coordinator at shantil.moyer@brambleton.org