BCA Update - Spring/Summer

Asphalt Seal Coating Project: Group Two

Group Two of the seal coating project is scheduled for Wednesday, September 6th.  The below streets will be closed for a 24-hour period so that the seal coat can be applied and have time to dry. All travel and parking on these streets will be prohibited during this time.  

Group 2 – Wednesday, September 6th  
  • Cedar Crest Alley
  • Melville Terrace
  • Moon Beam Terrace (North side)
  • Parkland Farms (West side of Parkland Farms between Moon Beam Terr & Highcroft Terr)
  • Redeemer Terrace (between Snow Powder & Faith Terr)
  • Redeemer Terrace (South side of Redeemer between Faith Terr & Belmont Ridge Rd)
  • Vienna Green Terrace

Please note that the Redeemer Parking Lots across from Winwood will be reserved for Winwood drop-off/pickup only.  No resident parking in lot permitted on Wednesday between 6:00 AM and 7:00 PM.  Residents can use lot for parking after 7:00 PM.

Please review MAP and the above listed “Green” streets that will be closed.
 
RELOCATING VEHICLES: Vehicles remaining on these streets after 7:00 AM will be relocated to the Brambleton Ballfield parking lot or adjacent street by a tow company. Vehicles in residents’ driveways and garages will also need to be relocated by the owners if they plan or need to use their vehicle during the 24-hour road closure period. **Please be cautious of parking vehicles on other BCA streets that are scheduled to be seal coated, as similar restrictions and relocation efforts will also take place. 

ACCESS TO STREETS:  All access to the streets during this time is restricted.  Freshly applied seal coating will track.  Be sure to stay off the streets.  If applicable, educate and inform your children; also keep your pets off.  BCA will place plywood down in strategic locations to serve as crossing points for pedestrians.  

IRRIGATION SYSTEMS: If applicable, residents must turn off their irrigation systems during this 24-hour period.  Wet streets or water sprayed onto freshly seal coated streets will negatively impact the application.  BCA will also be turning its systems off in the area of the treated streets.  

FURTHER INFORMATION: It is important that all affected residents understand how they will be impacted.  Please review the full information packet that was distributed to all impacted addresses.  This information is also on the BCA website at www.BrambletonHOA.com/asphalt.   If you have questions after reading this information, please email BCA's Capital Projects Coordinator at CIP@brambleton.org